Project Schedule
Upcoming and Current Activities
(estimated or subject to change)
Approximate Date | Milestone |
---|---|
August 2026 | EM&CP for Cicero Substation to be filed |
April 2027 | Cicero Substation construction work scheduled to begin |
March 2029 | Construction work scheduled to be complete |
Project Milestone Schedule
Date | Milestone |
---|---|
May 2015 | Article VII Application Submitted |
June 2019 | Environmental Management and Construction Plan (EM&CP) for the transmission line work approved |
August 2019 | Transmission line rebuild construction work begins |
February 2021 | Transmission line rebuilt and placed into service |
February 2022 | Transmission line construction restoration work completed |