News and Updates

2023

No work took place on site last week. The Augustina Avenue Upgrade project is now complete. 

This week neighbors can expect to see: 

  • Possible continuation of restoration punch list items.

No work took place on site last week. The Augustina Avenue Upgrade project is now complete. 

This week neighbors can expect to see: 

  • Possible continuation of restoration punch list items.

No work took place on site last week. The Augustina Avenue Upgrade project is now complete. 

This week neighbors can expect to see: 

  • Possible continuation of restoration punch list items.

No work took place on site last week. The Augustina Avenue Upgrade project is now complete. 

This week neighbors can expect to see: 

  • Continued restoration punch list items.

Last week our team completed the restoration of the sidewalk and curb on Augustina Avenue on 11/3/23.

This week neighbors can expect to see: 

  • Continued restoration punch list items.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our team completed restoration of the sidewalk and curb on Augustina Avenue. Residents can once again expect a limited presence on site, with the full mill and paving of Augustina Avenue expected to be completed on Tuesday 11/7. 

This week neighbors can expect to see:

  • Full curb to curb restoration of Augustina Avenue on Tuesday 11/7.

*Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our team completed restoration of the sidewalk on Augustina Avenue. Residents can once again expect a limited presence on site, with full restoration of Augustina Avenue expected to be completed over the next few weeks. 

This week neighbors can expect to see: 

  • A limited presence on site.
  • Preparations for full curb to curb restoration of Augustina Avenue.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our Instrumentation and Regulation team continued with their work, as this project moves closer to completion. Residents can once again expect a limited presence on site, with full restoration of Augustina Avenue expected to be completed over the next few weeks. 

This week neighbors can expect to see: 

  • A limited presence on site.
  • Preparations for full curb to curb restoration of Augustina Avenue.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our Instrumentation and Regulation team put the new station into service.  

 This week neighbors can expect to see: 

  • A limited presence on site.
  • Preparations for full curb-to-curb restoration of Augustina Avenue.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team worked inside the OPP and secondary vaults and walked the site with our contractor team to discuss restoration. Hawkeye was also on site to complete electrical work. 

This week neighbors can expect to see: 

  • Work by our Instrumentation and Regulation team.
  • Restoration of Augustina Avenue beginning on 10/16.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued permanent restoration of Augustina Ave, Minton Street, and Beach 12th Street. Restoration work will continue through the month of September. PSEG was also on site to install electrical connections. 

This week neighbors can expect to see: 

  • Continued restoration of all three roadways through the month of September.
  • Work by our Instrumentation and Regulation team.
  • Removal of any leftover materials from Beach 12th Street.
  • Curb to Curb restoration will take place from 10/9 - 10/20.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued Permanent restoration of Augustina Ave, Minton Street, and Beach 12th Street. Restoration work will continue through the month of September. 

This week neighbors can expect to see: 

  • Permanent restoration of  all three roadways through the month of September.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Removal of any leftover materials from Beach 12th Street.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued backfilling of excavations and continued temporary road restoration. 

This week neighbors can expect to see: 

  • Permanent restoration of the roadway through the month of September.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.

 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued backfilling of excavations and continued temporary road restoration. 

This week neighbors can expect to see: 

  • Continued backfilling of excavations on Augustina Avenue and Minton Street.
  • Continued temporary restoration of Augustina Avenue and Minton Street.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued backfilling of excavations and began temporary road restoration. 

This week neighbors can expect to see: 

  • Continued backfilling of excavations on Augustina Avenue and Minton Street.
  • Continued temporary restoration of Augustina Avenue and Minton Street.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team painted and coated new infrastructure, installed new man hole lids and frames, continued backfilling of excavations and began temporary restoration of Augustina Avenue and Minton Street, and removed old vent poles. 

This week neighbors can expect to see: 

  • Continued backfilling of excavations on Augustina Avenue and Minton Street.
  • Temporary restoration of Augustina Avenue and Minton Street.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued backfilling of excavations on Augustina Avenue and Minton Street, water-proofed and coated new infrastructure, installed vent poles, performed tie-in work, and installed new vault lids. 

This week neighbors can expect to see: 

  • Continued backfilling of excavations on Augustina Avenue and Minton Street.
  • Temporary restoration of Augustina Avenue and Minton Street.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team installed vent poles, performed tie-in work, backfilled excavations on Augustina Avenue and Minton Street, and installed new vault lids. 

This week neighbors can expect to see: 

  • Continued backfilling of excavations on Augustina Avenue and Minton Street.
  • Vault water-proofing and coating by Enecon. 
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued backfilling of excavations, installed conduit and test stations, and performed tie-in work. National Grid's Instrumentation & Regulation team was also on site to test valves and flanges.

This week neighbors can expect to see: 

  • Installation of vault lids on 8/9.
  • Installation of new vent poles.
  • Continued backfilling along Augustina Avenue and Minton Street.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued underground infrastructure work within our pit with Enecon and extended our trench on Minton Street to the opposite curb.

This week neighbors can expect to see: 

  • On Thursday, 8/3/23 we will have a crane on site to install vault lids.
  • Continued underground infrastructure work within our pit by Enecon.
  • Backfilling along Augustina Avenue and Minton Street.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team supported Enecon as they performed underground infrastructure work within our pit on Augustina Avenue. 

This week neighbors can expect to see: 

  • Continued underground infrastructure work within our pit by Enecon.
  • Extension of our trench on Minton Street so it meets the opposite curb line. 
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team performed pressure testing on Friday 7/14, which can result in louder than normal work conditions on site. We thank you for your continued patience as we completed that important stage of the project.  Our crews also continued work to install control lines, and continued welding. 

This week neighbors can expect to see: 

  • Underground infrastructure work within our pit by Enecon.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team worked on installing control lines and continued welding. 

This week neighbors can expect to see: 

  • Pressure testing.
  • Continued work on control lines.
  • Continued welding.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.

Pressure testing will begin for this project on our about 7/10/23. Residents may notice elevated noise levels as a result of this work. Pressure testing will take approximately one week to complete.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team worked on installing control lines and continued welding. 

This week neighbors can expect to see: 

  • Continued work on control lines.
  • Continued welding.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.
 

Pressure testing will begin for this project on our about 7/10/23. Residents may notice elevated noise levels as a result of this work. Pressure testing will take approximately one week to complete.

 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team installed control lines, installed new pipe on Minton Street, continued underground vault work on Augustina Avenue, and continued welding. 

This week neighbors can expect to see: 

  • Possible widening of excavations on Augustina Avenue.
  • Continued pipe installation on Minton Street.
  • Continued welding.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued underground vault work on Augustina Avenue, excavation and pipe installation on Minton Street, and welding on Augustina Avenue. 

This week neighbors can expect to see: 

  • Installation of control lines.
  • Possible widening of excavations on Augustina Avenue.
  • Continued pipe installation on Minton Street.
  • Continued underground vault work on Augustina Avenue.
  • Continued welding.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued underground vault work on Augustina Avenue and continued welding operations and pipe installation on Augustina Avenue. 

This week neighbors can expect to see: 

  • Pipe installation on Minton Street.
  • Continued underground vault work on Augustina Avenue.
  • Continued welding.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team continued welding operations and pipe installation on Augustina Avenue. 

This week neighbors can expect to see: 

  • Continued underground vault work on Augustina Avenue.
  • Continued welding.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week our construction team excavated a small trench across Minton Avenue and performed underground vault work and welding on Augustina Ave.

This week neighbors can expect to see: 

  • Continued underground vault work on Augustina Avenue.
  • New pipe installation.
  • Welding.
  • Continued road closure on Augustina Avenue between Minton Street and Beach 12th Street.
  • Continued material storage on Beach 12th Street between Augustina Avenue and Central Avenue.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

No work took place at the site last week. 

This week neighbors can expect to see: 

  • Possible trench excavation across Minton Avenue.
  • Underground vault work on Augustina Avenue.
  • Welding.

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week, our crews used a crane on site to lift out existing underground vaults on Augustina Avenue.

This week neighbors can expect to see: 

  • Possible tree pruning on Augustina Avenue.
  • Possible trench excavation across Minton Avenue.
  • Preparations for new vault delivery on Augustina Avenue.
  • Welding.
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week, our crews continued underground vault work in preparation for vault replacement and performed road grading, both on Augustina Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see: 

  • Continued underground vault work.
  • Preparations for crane lifts the following week.
 

 *Due to the complexity of outside construction, schedule is subject to change

Last week, our crews continued with excavations and underground vault work on Augustina Avenue. Excavations for test pits on Beach 12th Street have been plated and secured and Beach 12th Street is now open to traffic.

This week neighbors can expect to see:

  • Grading of Augustina Avenue in preparation for vault installations.
  • Installation of new underground vaults on Augustina Avenue.
  • Augustina Avenue closed to through traffic between Beach 12th Street and Minton Street. 
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week, our crews performed excavations and underground vault work on Augustina Avenue and excavations for test pits on Beach 12th Street.  

This week neighbors can expect to see:

  • Continued excavation on Augustina Avenue.
  • Continued underground vault work on Augustina Avenue.
  • Augustina Avenue closed to through traffic between Beach 12th Street and Minton Street. 

 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week, our crews performed excavation, backfilling and underground vault work on Augustina Avenue, and backfilling and temporary restoration of test pits on Beach 12th Street.  

This week neighbors can expect to see:

  • Continued excavation and backfilling on Augustina Avenue.
  • Underground vault work on Augustina Avenue.
  • Augustina Avenue closed to through traffic between Beach 12th Street and Minton Street. 
 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Last week, construction began with excavation on Augustina Avenue and on Beach 12th Street where test pits were needed to determine next steps. Materials will be stored on the sidewalk of Beach 12th Steet between Augustina Avenue and Central Avenue for the duration of the project. 

This week neighbors can expect to see:

  • Continued excavation and backfilling on Augustina Avenue.
  • Underground vault work on Augustina Avenue.
  • Augustina Avenue closed to through traffic between Beach 12th Street and Minton Street. 

Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.