Construction Schedule
The timeline below is approximate and subject to change. The timeline will be updated as construction progresses.
Activity | Approximate Date |
---|---|
Phase 1 Start | March 2024 |
Phase 1 End | September 2024 |
Phase 2 Start | September 2024 |
Phase 2 Pause | October 2024 |
Phase 2 Resumes | Spring 2026 |
Phase 2 End | Fall 2026 |
Final Restoration | Fall 2026 |