Skip to main content

News and Updates

2024

In July 2024, neighbors can expect to see the following activities:

  • NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
  • Excavation activities.
  • Installation of upgraded infrastructure.
  • Welding activities.

In June 2024, neighbors can expect to see the following activities:

  • NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
  • Excavation activities.
  • Installation of upgraded infrastructure.
  • Welding activities.
  • Crane/heavy machinery operations for vault installation.

In May 2024, neighbors can expect to see the following activities:

  • NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
  • Our contractor Hallen mobilizing materials, machines, and a trailer on-site.
  • Sidewalk excavations on Willow Avenue and Bay Street for installation of new infrastructure.
  • Soil sampling activities.
  • Con Edison to de-energize lines to accommodate future upgrades.
  • Welding activities.
  • Quality assurance testing activities scheduled on 5/13.
  • Critical lift tentatively scheduled for 05/24.
  • Roof removal activities.
  • Air monitoring activities for asbestos abatement.