News and Updates
2024
In November 2024, neighbors can expect to see the following activities:
- Roof installation.
- Backfilling and temporary restoration activities.
- Final restoration activities.
In October 2024, neighbors can expect to see the following activities:
- Cleaning of infrastructure which requires 24-hour crew presence.
- Welding activities.
- October 11th through October 14th, extended work hours and weekend work, 7AM to 8PM*, for tie in activities mentioned above. Neighbors can expect intermittent road closures on Bay Street and Willow Avenue. Traffic flaggers will be on-site to assist local traffic.
In September 2024, neighbors can expect to see the following activities:
- Installation of upgraded infrastructure.
- Welding activities.
- Potential tie-in activities.
- Quality assurance testing.
In August 2024, neighbors can expect to see the following activities:
- Excavation activities.
- Installation of upgraded infrastructure.
- Welding activities.
In July 2024, neighbors can expect to see the following activities:
- NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
- Excavation activities.
- Installation of upgraded infrastructure.
- Welding activities.
In June 2024, neighbors can expect to see the following activities:
- NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
- Excavation activities.
- Installation of upgraded infrastructure.
- Welding activities.
- Crane/heavy machinery operations for vault installation.
In May 2024, neighbors can expect to see the following activities:
- NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
- Our contractor Hallen mobilizing materials, machines, and a trailer on-site.
- Sidewalk excavations on Willow Avenue and Bay Street for installation of new infrastructure.
- Soil sampling activities.
- Con Edison to de-energize lines to accommodate future upgrades.
- Welding activities.
- Quality assurance testing activities scheduled on 5/13.
- Critical lift tentatively scheduled for 05/24.
- Roof removal activities.
- Air monitoring activities for asbestos abatement.