News and Updates

2024

In November 2024, neighbors can expect to see the following activities:

  • Roof installation.
  • Backfilling and temporary restoration activities.
  • Final restoration activities.

In October 2024, neighbors can expect to see the following activities:

  • Cleaning of infrastructure which requires 24-hour crew presence.
  • Welding activities.
  • October 11th through October 14th, extended work hours and weekend work, 7AM to 8PM*, for tie in activities mentioned above. Neighbors can expect intermittent road closures on Bay Street and Willow Avenue. Traffic flaggers will be on-site to assist local traffic.

In September 2024, neighbors can expect to see the following activities:

  • Installation of upgraded infrastructure.
  • Welding activities.
  • Potential tie-in activities.
  • Quality assurance testing.

In August 2024, neighbors can expect to see the following activities:

  • Excavation activities.
  • Installation of upgraded infrastructure.
  • Welding activities.

In July 2024, neighbors can expect to see the following activities:

  • NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
  • Excavation activities.
  • Installation of upgraded infrastructure.
  • Welding activities.

In June 2024, neighbors can expect to see the following activities:

  • NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
  • Excavation activities.
  • Installation of upgraded infrastructure.
  • Welding activities.
  • Crane/heavy machinery operations for vault installation.

In May 2024, neighbors can expect to see the following activities:

  • NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
  • Our contractor Hallen mobilizing materials, machines, and a trailer on-site.
  • Sidewalk excavations on Willow Avenue and Bay Street for installation of new infrastructure.
  • Soil sampling activities.
  • Con Edison to de-energize lines to accommodate future upgrades.
  • Welding activities.
  • Quality assurance testing activities scheduled on 5/13.
  • Critical lift tentatively scheduled for 05/24.
  • Roof removal activities.
  • Air monitoring activities for asbestos abatement.