Skip to main content

News and Updates

2025

Neighbors can expect to see:

  • Final restoration activities

Note: There will be minimal impacts to traffic on Willow Avenue and Bay Street. Traffic flaggers will be present to direct vehicular and pedestrian traffic as necessary. 

Neighbors can expect to see:

  • Continued civil work: installing a roof and upgrading control lines
  • Continued restoration activities

Note: There will be minimal impacts to traffic on Willow Avenue and Bay Street. Traffic flaggers will be present to direct vehicular and pedestrian traffic as necessary. 

In February 2025, neighbors can expect to see:

  • Continued civil work: installing a roof and upgrading control lines
  • Continued restoration activities

In January 2025, neighbors can expect to see the following activities:

  • Continued civil work
  • Restoration activities

2024

In December 2024, neighbors can expect to see the following activities:

  • Continued improvements to the roof
  • Continued civil work
  • Backfilling and temporary restoration activities

In November 2024, neighbors can expect to see the following activities:

  • Roof installation.
  • Backfilling and temporary restoration activities.
  • Final restoration activities.

In October 2024, neighbors can expect to see the following activities:

  • Cleaning of infrastructure which requires 24-hour crew presence.
  • Welding activities.
  • October 11th through October 14th, extended work hours and weekend work, 7AM to 8PM*, for tie in activities mentioned above. Neighbors can expect intermittent road closures on Bay Street and Willow Avenue. Traffic flaggers will be on-site to assist local traffic.

In September 2024, neighbors can expect to see the following activities:

  • Installation of upgraded infrastructure.
  • Welding activities.
  • Potential tie-in activities.
  • Quality assurance testing.

In August 2024, neighbors can expect to see the following activities:

  • Excavation activities.
  • Installation of upgraded infrastructure.
  • Welding activities.

In July 2024, neighbors can expect to see the following activities:

  • NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
  • Excavation activities.
  • Installation of upgraded infrastructure.
  • Welding activities.

In June 2024, neighbors can expect to see the following activities:

  • NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
  • Excavation activities.
  • Installation of upgraded infrastructure.
  • Welding activities.
  • Crane/heavy machinery operations for vault installation.

In May 2024, neighbors can expect to see the following activities:

  • NOTE: Crews will be working Saturdays through the duration of the project to increase productivity.
  • Our contractor Hallen mobilizing materials, machines, and a trailer on-site.
  • Sidewalk excavations on Willow Avenue and Bay Street for installation of new infrastructure.
  • Soil sampling activities.
  • Con Edison to de-energize lines to accommodate future upgrades.
  • Welding activities.
  • Quality assurance testing activities scheduled on 5/13.
  • Critical lift tentatively scheduled for 05/24.
  • Roof removal activities.
  • Air monitoring activities for asbestos abatement.