Last week, our team was on site to perform restoration work on Sayville Avenue. This restoration work is expected to continue this week.
Our team may be on site this week to perform restoration work on Sayville Avenue, near the intersection of 13th Street.
*Please note, due to complexities of outdoor construction, schedule is subject to change.
2022
Last week our crews finalized temporary restoration work. This project is now complete. The final mill and pave of Sayville Avenue will take place in the Spring of 2023.
Last week our crews continued restoration work. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Continued restoration of the project site.
*Construction schedule is subject to change
Last week our Instrumentation and Regulation team finished preparing the station for gas-in. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Continued restoration of the project site.
*Construction schedule is subject to change
Last week our Instrumentation and Regulation team continued preparing the station for gas-in. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Continued restoration of the site.
*Construction schedule is subject to change
Last week our Instrumentation and Regulation team prepared the station for gas-in. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Continued work by National Grid’s Instrumentation and Regulation team.
*Please note our construction schedule has changed. I&R crews will be working on site from 7AM to 9PM each day, including weekends, until November 23rd.
Last week our construction team installed pipe stands and began lawn restoration for affected properties. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Station inspection and commissioning by National Grid’s Instrumentation and Regulation team.
*Construction schedule is subject to change
Last week our construction team installed vault chimneys, ladders, and manhole covers. Temporary restoration was completed including restoration of concrete curbs. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Station inspection and commissioning by National Grid’s Instrumentation and Regulation team.
*Construction schedule is subject to change
Last week our construction team continued backfilling, paving and restoration work, installed vault covers, performed grading work around manholes, and painted vent poles. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Vault work to prepare new infrastructure to be put in service.
*Construction schedule is subject to change
Last week our construction team installed manholes and vault lids, waterproofed underground infrastructure, and performed paving and concrete work. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Continued paving and restoration work.
- Continued backfilling of excavations.
*Construction schedule is subject to change
Last week our construction team performed the installation of manholes and lids, waterproofing of underground infrastructure, sandblasting of underground infrastructure, and continued backfilling of excavations. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic, as necessary.
This week neighbors can expect to see:
- Continuing backfill and restoration.
- Installing final vault lids.
*Construction schedule is subject to change
Last week our construction team performed electrical work, tie-ins, installed vent poles, and backfilled excavations along Sayville Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Installation of manholes and lids.
- Waterproofing of underground infrastructure
- Sandblasting of underground infrastructure
- Continued backfilling of excavations
Last week our construction team performed concrete pouring, electrical work, underground vault work, tie-ins of underground utility lines, and water-proofing of underground infrastructure. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Continued electrical work
- Vent pole installation
- Partial backfilling of excavations
*Construction schedule subject to change
Last week our construction team performed work on underground vaults, vent poles, and tie-ins of underground utility lines. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Electrical work
- Continued underground vault work
- Continued tie-ins of underground utility lines
- Waterproofing of underground infrastructure
*Construction Schedule is subject to change
Last week our construction team performed excavations, backfilling, concrete work and vault work. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Continued underground vault work
- Tie-ins of underground utility lines
*Construction schedule is subject to change
Last week our construction team performed vault work and pressure testing. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Minor excavations
- Underground vault work
- Concrete work
*Construction schedule is subject to change
Last week our construction team performed pressure testing. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Underground infrastructure work
- Fabrication of vent lines
- Valve installations
- Vent pole relocation
*Construction schedule is subject to change
Last week our construction team completed welding and other underground infrastructure maintenance. Please note that parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.
This week neighbors can expect to see:
- Pressure testing
Last week our construction team performed underground infrastructure maintenance along Sayville Avenue. Please note that parking availability will be affected near active work areas.
This week neighbors can expect to see:
- Continued maintenance work on underground infrastructure.
- Sunday - No work scheduled
- Monday - Friday - Welding station infrastructure
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Friday - Welding station infrastructure
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Friday - Welding station infrastructure
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Friday - Welding station infrastructure
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Friday - Welding station infrastructure
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Holiday - No work scheduled
- Tuesday - Friday - Welding / fabricating inside vaults
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Friday - Welding / pre-fabrication / fabricating inside vaults
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Friday - Welding / pre-fabrication / fabricating inside vaults
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Friday - Welding / pre-fabrication / fabricating inside vaults
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Friday - Welding/Fabricating inside vaults
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - No work scheduled - Memorial Day
- Tuesday - Wednesday - Excavation
- Thursday - Friday - Prefabrication/Welding
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Tuesday - Unbolt existing regulator equipment in vaults
- Wednesday - Excavate control line & infrastructure
- Thursday -Vault delivery / install the new OPP Vault (Bay Crane on site)
- Friday - Excavate control line & infrastructure
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Wednesday - Excavation on Sayville Avenue around existing primary and secondary vaults and remove lids
- Thursday - Friday - Remove vault components
- Saturday - No work scheduled
Please note: Schedule is subject to change
- Sunday - No work scheduled
- Monday - Excavation on Sayville Avenue with vacuum truck
- Tuesday - Thursday - equipment cut and caps
- Friday - Excavation around existing primary and secondary vaults on Sayville Avenue and remove of lids
- Saturday - No work scheduled
Please note: Schedule is subject to change