The project is scheduled to start on 27 April 2022 through September 2022. Updated construction schedule will be posted online. Check back weekly for news and updates.
In the roadway area and the sidewalk of Sayville Avenue and 13th Street, Bohemia NY.
The work involves the refurbishment of an existing regulator station, control lines, electrical and mechanical telemetry cabinet, vent poles, and Over Pressure Protection (OPP).
National Grid is making investments to reinforce the local delivery system in your neighborhood to ensure customers receive safe and reliable energy service. This project will build a more reliable local natural energy system by reinforcing local underground infrastructure.
Yes. National Grid’s top priority is the safety of its customers, the general public, and its employees and contractors. The professional construction firms we work with also place safety as their top priority.
No. This work will be managed so that service interruption will not be an issue.
Construction is set to start on 27th April 2022 and will continue through September 2022. Restoration of the area will occur in September 2022.
Traffic will be impacted during construction along the project route. Our team is working with the town to ensure the safety of the streets on which our work will take place and mitigate traffic issues to the greatest extent feasible. Signs will be posted near streets and a traffic flagger will be on-site during construction hours.
If National Grid requires to dig on someone’s property, a proper easement will be secured before any digging happens. For this project, most of the excavation will happen on the street, sidewalk, and occasional grassy area of our right of way. Any disturbances to any surface will be repaired by National Grid at no cost to the impacted resident.
While our contractors will make efforts to keep disturbance to a minimum, there will be noise associated with this project. Most of that noise will occur while excavation is underway as contractors use heavy equipment to trench ahead of the work.
Please call our line (631-755-5338) or email Box.liprojects@nationalgrid.com to speak with a member of our outreach team. We also have a “news and update” session on this webpage —featuring regular construction updates with information regarding work locations and timelines.