Project Schedule

Upcoming and Current Activities

(estimated or subject to change)

December 2024-March 2025: Crews will work on civil construction related to the new substation. During this time, you may see trees and stumps being removed and stone brought to the site. Pouring and installation of concrete foundations will follow to accommodate substation equipment.

April 2025-May 2025: Our overhead line crews will upgrade the distribution and sub-transmission structures at the substation site, and along State Route 28. You may experience occasional traffic delays during this time.

June 2025-August 2025: Crews will cutover the service from the existing substation to the new substation. Raquette Lake customers may experience a short, temporary outage while this cutover is conducted. We will provide advance notice of when the outage will occur.

August 2025-September 2025: Following energization of the new substation, the former substation will be retired and torn down, and grass will be planted at the site.