Construction Schedule
Based on the estimated construction schedule, the following is a timeline of construction activities. Please note that the schedule is subject to change due to changes or delays in construction raised by the risk assessment, as well as the construction contractor. The timeline will be updated as the project planning progresses.
Action | Approximate Date |
---|---|
Phase 1: Demolition of existing concrete structures |
Spring 2024 - Summer 2024 |
Phase 2: Installation of upgraded sewer system |
Fall 2024 - Spring 2025 |
Phase 3: Building of upgrading maintenance building |
Summer 2025 - Spring 2026 |
Phase 4: Completion and commissioning of the new maintenance building |
Fall 2026 |