Construction Schedule

Based on the estimated construction schedule, the following is a timeline of construction activities. Please note that the schedule is subject to change due to changes or delays in construction raised by the risk assessment, as well as the construction contractor. The timeline will be updated as the project planning progresses.

Action Approximate Date

Phase 1: Demolition of existing concrete structures

Spring 2024 - Summer 2024

Phase 2: Installation of upgraded sewer system

Fall 2024 - Spring 2025

Phase 3: Building of upgrading maintenance building

Summer 2025 - Spring 2026

Phase 4: Completion and commissioning of the new maintenance building

Fall 2026