News and Updates

*IMPORTANT PARKING/TRAFFIC PATTERN CHANGE NOTICE: Parking near the work zone will be prohibited during and after construction hours. Traffic on Bennett Avenue will be a two-way, stop-and-go traffic flow with traffic flaggers on-site. For your safety, please be mindful of work zones, signs, and personnel.

Last week trained contractors milled and paved Bennett Avenue. This project is now complete.

Final restoration activities are underway. This work in anticipated to take 1-2 weeks to complete.

* TRAFFIC IMPACTS AND TEMPORARY ROAD CLOSURES ON BENNETT AVENUE DURING RESTORATION ACTIVITIES. PLEASE STAY OUT OF THE WORK ZONE AND USE TRAFFIC FLAGGERS FOR ASSISTANCE.

Final restoration activities are underway. This work in anticipated to take 1-2 weeks to complete.

* TRAFFIC IMPACTS AND TEMPORARY ROAD CLOSURES ON BENNETT AVENUE DURING RESTORATION ACTIVITIES. PLEASE STAY OUT OF THE WORK ZONE AND USE TRAFFIC FLAGGERS FOR ASSISTANCE. * 

Final restoration is set to begin as early as 08/19/2024 and is anticipated to take 1-2 weeks.
 

* TRAFFIC IMPACTS AND TEMPORARY ROAD CLOSURES ON BENNETT AVENUE DURING RESTORATION ACTIVITIES. PLEASE STAY OUT OF THE WORK ZONE AND USE TRAFFIC FLAGGERS FOR ASSISTANCE. * 

Final restoration is set to begin as early as 08/19/2024 and is anticipated to take 1-2 weeks.
 

* TRAFFIC IMPACTS AND TEMPORARY ROAD CLOSURES ON BENNETT AVENUE DURING RESTORATION ACTIVITIES. PLEASE STAY OUT OF THE WORK ZONE AND USE TRAFFIC FLAGGERS FOR ASSISTANCE. * 

Last week our crews began final restoration.

 This week neighbors can expect:

  • Continue final restoration of the roadway and/or impacted areas from construction.
  • Demobilizing from the site.
     

* TRAFFIC IMPACTS AND TEMPORARY ROAD CLOSURES ON BENNETT AVENUE DURING CONSTRUCTION HOURS. PLEASE STAY OUT OF THE WORK ZONE AND USE TRAFFIC FLAGGERS FOR ASSISTANCE. * 

Last week our crews began backfilling excavations and temporary restoration.

 This week neighbors can expect:

  • Begin final restoration of the roadway and/or impacted areas from construction.
     

* TRAFFIC IMPACTS AND TEMPORARY ROAD CLOSURES ON BENNETT AVENUE DURING CONSTRUCTION HOURS. PLEASE STAY OUT OF THE WORK ZONE AND USE TRAFFIC FLAGGERS FOR ASSISTANCE. * 

Last week our crews began wrapping infrastructure and backfilling excavations.

 This week neighbors can expect:

  • Continued backfill of excavations.
  • Begin temporary restoration of the area.

* TRAFFIC IMPACTS AND TEMPORARY ROAD CLOSURES ON BENNETT AVENUE DURING CONSTRUCTION HOURS. PLEASE STAY OUT OF THE WORK ZONE AND USE TRAFFIC FLAGGERS FOR ASSISTANCE. * 

Last week our crews had a crane on-site to install upgraded infrastructure and to test the installation for operational use.

 This week neighbors can expect:

  • Continued tests on upgraded infrastructure.
  • Our in-house construction team on site to perform tie in activities where they connect the existing infrastructure to the upgraded infrastructure.
  • Welding activities.
 

* TRAFFIC IMPACTS AND TEMPORARY ROAD CLOSURES ON BENNETT AVENUE DURING CONSTRUCTION HOURS. PLEASE STAY OUT OF THE WORK ZONE AND USE TRAFFIC FLAGGERS FOR ASSISTANCE. * 

The Bennett Avenue Upgrade project will be resuming this Sunday, 7/7/24.

 This week neighbors can expect:

  • Our Instrumentation & Regulation team on site Sunday, 7/7.
  • Our in-house construction team on site to perform mandated testing of upgraded infrastructure. 
  • Prep work for crane on site.
  • Welding.

Last week our contractors continued excavating on Bennett Avenue between Westbury Boulevard and Elk Street.

This week the neighborhood can expect to see:

  • Continued excavations on Bennett Avenue.
  • Intermittent road closures on Bennett Avenue between Westbury Boulevard and Elk Street.
 

Construction activities will be paused from 06/09/2024 to 07/07/2024.

Last week our contractors began mobilizing and excavating on Bennett Avenue between Westbury Boulevard and Elk Street.

This week the neighborhood can expect to see:

  • Continued excavations on Bennett Avenue.
  • Intermittent road closures on Bennett Avenue between Westbury Boulevard and Elk Street.
  • No work on Monday, May 27, 2024.

This week the neighborhood can expect to see:

  • Asplundh mobilizing materials and construction equipment on-site.
  • Marking out of underground utilities.
  • Excavations on Bennett Avenue between Westbury Boulevard and Elk Street.