Last week our crews continued excavation, backfilling, and underground infrastructure upgrades on Vanderbilt Avenue, between Dean Street and Bergen Street. Our Corrosion Team was also on site performing gas main work in preparation for replacement. 

At the end of each work day, all excavations will be secured and plated for vehicle and pedestrian safety. Crews will end their work day at 3PM on Fridays to open the street in compliance with the NYC Open Streets Program. 

This week, neighbors can expect: 

  • Continued excavation and underground infrastructure work on Vanderbilt Avenue, between Dean Steet and Bergen Street. 
  • Continued storage of materials and equipment on Bergen Street.
  • Continued impacts to traffic and parking on Vanderbilt Avenue and Bergen Street.

*Due to the complexity of outside construction, schedule is subject to change. For your safety, please do not enter work zones.*

Last week our crews continued excavation, backfilling, and underground infrastructure upgrades on Vanderbilt Avenue, between Dean Street and Bergen Street. 

At the end of each work day, all excavations will be secured and plated for vehicle and pedestrian safety. Crews will end their work day at 3PM on Fridays to open the street in compliance with the NYC Open Streets Program. 

This week, neighbors can expect: 

  • Continued excavation and underground infrastructure work on Vanderbilt Avenue, between Dean Steet and Bergen Street. 
  • Continued storage of materials and equipment on Bergen Street.
  • Continued impacts to traffic and parking on Vanderbilt Avenue and Bergen Street.
 

*Due to the complexity of outside construction, schedule is subject to change. For your safety, please do not enter work zones.*

Last week our crews continued excavation, backfilling, and underground infrastructure upgrades on Vanderbilt Avenue, between Dean Street and Bergen Street. 

At the end of each work day, all excavations will be secured and plated for vehicle and pedestrian safety. Crews will end their work day at 3PM on Fridays to open the street in compliance with the NYC Open Streets Program. 

This week, neighbors can expect: 

  • Continued excavation and underground infrastructure work on Vanderbilt Avenue, between Dean Steet and Bergen Street. 
  • Continued storage of materials and equipment on Bergen Street.
  • Continued impacts to traffic and parking on Vanderbilt Avenue and Bergen Street.

 

*Due to the complexity of outside construction, schedule is subject to change. For your safety, please do not enter work zones.*

Last week our crews continued excavation, backfilling, and underground infrastructure upgrades on Vanderbilt Avenue, between Dean Street and Bergen Street. 

At the end of each work day, all excavations will be secured and plated for vehicle and pedestrian safety. Crews will end their work day at 3PM on Fridays to open the street in compliance with the NYC Open Streets Program.  

This week, neighbors can expect: 

  • Continued excavation and underground infrastructure work on Vanderbilt Avenue, between Dean Street and Bergen Street. 
  • Continued storage of materials and equipment on Bergen Street.

*Due to the complexity of outside construction, schedule is subject to change. For your safety, please do not enter work zones.*

Last week our crews continued excavation, backfilling, and underground infrastructure upgrades on Vanderbilt Avenue, between Dean Street and Bergen Street. 

At the end of each work day, all excavations will be secured and plated for vehicle and pedestrian safety. Crews will end their work day at 3PM on Fridays to open the street in compliance with the NYC Open Streets Program. 

This week, neighbors can expect: 

  • Continued excavation and underground infrastructure work on Vanderbilt Avenue, between Dean Steet and Bergen Street. 
  • Continued storage of materials and equipment on Bergen Street.
 

*Due to the complexity of outside construction, schedule is subject to change. For your safety, please do not enter work zones.*

Last week our crews continued work at the intersection of Vanderbilt Ave and Dean St, performing excavations, backfilling, and upgrading underground infrastructure.

At the end of each work day, all excavations will be secured and plated for vehicle and pedestrian safety. Crews will end their work day at 3 PM on Fridays to open the street in compliance with the NYC Open Streets Program.

This week, neighbors can expect:

  • Continued excavation and underground infrastructure work on Vanderbilt Avenue, between Dean Steet and Bergen Street.

*Due to the complexity of outside construction, schedule is subject to change. For your safety, please do not enter work zones.*

Last week our crews continued work at the intersection of Vanderbilt Ave and Dean St, performing excavations, backfilling and upgrading underground infrastructure. We also began excavating our second pit, directly adjacent to the existing pit, in front of 560 Vanderbilt Avenue. 

At the end of each work day, all excavations will be secured and plated for vehicle and pedestrian safety. Crews will end their work day at 3PM on Fridays to open the street in compliance with the NYC Open Streets Program. 

This week, neighbors can expect: 

  • Continued excavation and underground infrastructure work on Vanderbilt Avenue, between Dean Steet and Bergen Street. 
 

*Due to the complexity of outside construction, schedule is subject to change. For your safety, please do not enter work zones.*

Construction on the Prospect Heights Upgrade Project began last week with excavation on Vanderbilt Avenue near the intersection of Dean Street. In the coming weeks our crews will be digging a second excavation pit, directly adjacent to the existing pit, in front of 560 Vanderbilt Avenue. 

At the end of each work day, all excavations will be secured and plated for vehicle and pedestrian safety. Crews will end their work day at 3PM on Fridays to open the street in compliance with the NYC Open Streets Program. 

This week, neighbors can expect: 

  • Continued excavation and underground infrastructure work on Vanderbilt Avenue, between Dean Steet and Bergen Street. 
 

*Due to the complexity of outside construction, schedule is subject to change. For your safety, please do not enter work zones.*

Construction on the Prospect Heights Upgrade Project is scheduled to begin on our about 5/7/24. Our contractor team, Hallen Construction, will mobilize on site at Vanderbilt Avenue, between the intersections of Dean Street and Bergen Street, and begin excavations.

*Due to the complexity of outside construction, schedule is subject to change. For your safety, please do not enter work zones.*

Construction on the Prospect Heights Upgrade Project is scheduled to begin on our about 5/7/24. Our contractor team, Hallen Construction, will mobilize on site at Vanderbilt Avenue, between the intersections of Dean Street and Bergen Street, and begin excavations.

 