Project Schedule
Construction Activities:
- Construction of Marshalling Yards: Late Spring 2024
- Anticipated Construction Start: Fall 2024
- Anticipated Construction End: Fall 2026
Upcoming Activities:
2025
- Matting Reconfiguration in Le Ray near US Route 11, Jenkins Road - County Route 16 and NYS Route 37 to locations in Pamelia near Perch Lake Road to County Route 16 to Knowlesville Road
- Installation of Turtle Fencing in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37
- Site Restoration in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37
- Electrical and Civil Construction in Le Ray near US Route 11 at the Indian River Substation
- Matting Reconfiguration in Pamelia near Perch Lake Road to County Route 16 to Knowlesville Road
- Installation of Turtle Fencing and Barriers in Le Ray near US Route 11
- Site Restoration in Le Ray near US Route 11
- Electrical and Civil Construction in Le Ray near US Route 11 at the Indian River Substation
- Installation of Turtle Fencing and Barriers in Pamelia near Knowlesville Road and NYS Route 37
- Continued Wire Stringing (Pulling) Execution at Structure Locations in Le Ray near Jenkins Road - County Route 16 to NYS Route 37
- Matting Reconfiguration and Access Road Installation starting in Le Ray near US Route 11 to Parish Road to Bonney Road in Brownville
- Site Restoration in Le Ray near US Route 11
- Electrical and Civil Construction in Le Ray near US Route 11 at the Indian River Substation
- Structure Setting at Locations in Pamelia near NYS Route 37, Knowlesville Road, and Perch Lake Road
- Matting Reconfiguration starting in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37 in Pamelia to Knowlesville Road to Perch Lake Road to Parish Road to Bonney Road in Brownville
- No Structure Installation Work Scheduled
- Wire Stringing (Pulling) Execution at Structure Locations in Le Ray near Jenkins Road - County Route 16 and US Route 11
- Matting Reconfiguration starting in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37 in Pamelia to Knowlesville Road to Perch Lake Road to Parish Road to Bonney Road in Brownville
- Wire Stringing (Pulling) Execution at Structure Locations in Le Ray near Jenkins Road - County Route 16 and US Route 11
- Foundation Pouring at Structure Locations in Le Ray near NYS Route 37, and Jenkins Road - County Route 16 and US Route 11
- Matting Reconfiguration starting in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37 in Pamelia to Knowlesville Road to Perch Lake Road to Parish Road to Bonney Road in Brownville
- Foundation Pouring at Structure Location in Pamelia near Kowlesville Road
- Wire Stringing (Pulling) Preparation at Structure Locations in Le Ray near NYS Route 37, and Jenkins Road - County Route 16 and US Route 11
- Installation of Turtle Fencing in Pamelia near Knowlesville Road and NYS Route 37
- Matting Reconfiguration starting in Le Ray near US Route 11 to Jenkins Road - County Route 16 to NYS Route 37 in Pamelia to Knowlesville Road to Perch Lake Road to Parish Road to Bonney Road in Brownville
-
Structure Drilling and Concrete Filling at Structure Locations in Pamelia near NYS Route 37 and Knowlesville Road
-
Structure Drilling and Concrete Filling at Structure Locations in Pamelia near Knowlesville Road
- Structure Drilling and Rock Extraction at Structure Location in Pamelia near Kowlesville Road
-
Matting Installation and Construction of Gravel Access Roads in Brownville near Star School House Road and Bonney Road
-
Wire Stringing (Pulling) Preparation and Execution at Structure Locations in Le Ray near Jenkins Road - County Route 16 and US Route 11
- Concrete Pouring at Structure Location in Pamelia near NYS Route 37
- Structure Drilling and Concrete Filling at Structure Location in Pamelia near NYS Route 37
- Structure Drilling and Concrete Filling at Structure Location in Pamelia near NYS Route 37 and Knowlesville Road
- Matting Installation and Construction of Gravel Access Roads in Brownville near Star School House Road and Bonney Road
- Structure Drilling and Concrete Pouring at Structure Locations in Pamelia near NYS Route 37
- Transmission Line Structure Installation in Pamelia near NYS Route 37
- Matting in Pamelia near NYS Route 37 and Knowslesville Road
- Gravel Access Roads in Pamelia from NYS Route 37 up to Knowlesville Road
- Structure Drilling at Structure Locations in Le Ray near Jenkins Road - County Route 16
- Matting in Pamelia near NYS Route 37, NYS Route 37 and Knowlesville Road, and Knowlesville Road
- Transmission Line Preparation for Wire Pulling and Equipment Transfer to Indian River Substation near US Route 11, and US Route 11 and Jenkins Road - County Route 16
- Structure Drilling at Structure Locations in Le Ray near Jenkins Road - County Route 16
- Gravel Access Roads in Pamelia from Parish Road to Knowlesville Road
- Transmission Line Structure Installation in Le Ray from US Route 11 and Jenkins Road - County Route 16 and Jenkins Road - County Route 16
- Structure Drilling at Structure Locations in Le Ray near Jenkins Road - County Route 16, followed by Base Setting
- Foundation Pouring for Structure Location in Le Ray near US Route 11 and Jenkins Road (County Route 16)
- Installation of Galvanized Steel Poles at Structure Locations in Le Ray
- Drilling at Indian River Substation in Le Ray off Rogers Road
- Underground Foundation Construction at new North Watertown Substation Site in Brownville near Vaadi Road and NYS Route 12
- Foundation Pouring for Structure Location in Le Ray near US Route 11 and Jenkins Road (County Route 16)
- Materials and equipment will be transported via trucks to matted areas between Indian River Substation in Le Ray and Waddingham Road, near NYS Route 37 in Pamelia
- Structure Drilling at Structure Locations in Le Ray near US Route 11
- Foundation Pouring for Structure Location in Le Ray near US Route 11
- Materials and equipment will be transported via trucks to matted areas between Indian River Substation in Le Ray and Waddingham Road, near NYS Route 37 in Pamelia
- Foundation Pouring for Structure Location in Le Ray near US Route 11
- Structure Drilling at Structure Locations in Le Ray near US Route 11
- Materials and equipment will be transported via trucks to matted areas between Indian River Substation in Le Ray and Waddingham Road, near NYS Route 37 in Pamelia
2024
- No Work Tentatively Scheduled this Week
- No Work Scheduled this Week
- Construction of Access Road off of Parish Road (near Parish Cemetery)
- Clearing and Matting along the Project Corridor from NYS Route 37 to Waddingham Road in Pamelia
- Structure Drilling at Substation in Le Ray near US Route 11