Construction Schedule

Current Work Hours: 

  • Monday through Friday, 9AM to 2PM* (South Conduit between 128th St and 129th St)
  • Monday through Friday, 9AM to 2PM* (South Conduit between 129th St and 130th St)
  • Monday through Friday, 9AM to 2PM* (130th St between South Conduit and 150th Ave)
  • Monday through Friday, 7AM to 6PM* (130th St between 150th Ave and Old South Rd)
  • Monday through Friday, 7AM to 6PM* (Old South Rd between 128th St and 130th St)
 

Project Timeline: 

The timeline below is approximate and subject to change. The timeline will be updated as construction progresses. Please note that this project is multi-year with intermittent work. This schedule reflects planned construction starting in 2024.

Phase I (Brooklyn)

Milestone Approximate Date 
Construction Start March 2024
Final Restoration Start September 2024
Construction End October 2024

Phase II (Jamaica Bay East)

Milestone Approximate Date 
Construction Start November 2024
Final Restoration Start TBD
Construction End TBD