Frequently Asked Questions
This project will be located inside our Greenpoint Energy Facility in Brooklyn, NY.
Activities include demolition of the existing accommodations building, upgrades to the existing bulkhead, construction of the new saltwater pump house, and demolition of the previous saltwater pump house.
We are currently upgrading our Saltwater Pump House (SWPH) to increase the sustainability of the Greenpoint Energy Center in Brooklyn, NY. The SWPH is a required supplemental suppression system as part of the overall safety of the facility in the event of an emergency.
Work hours are Monday through Friday 7AM to 6PM.*
Yes. Our top priority is the safety of our customers, the public, employees, and contractors.
No. This upgrade is not a gas-related event.
Construction began in February 2022 and completion of this project is anticipated for Summer 2026.
Please call our hotline at 718-749-9819 or email Box.BKprojects@nationalgrid.com to speak with a member of our outreach team. We also have a dedicated project webpage: ngrid.com/saltwaterpump—featuring construction updates with information regarding specific activities and timelines.