News and Updates
2024
Last week crews continued backfilling and restoring Fulton Street and Grand Avenue. This week, neighbors can expect to see:
- Restoration activities: paving of the roadways and pouring of the concrete sidewalks
Last week crews began backfilling and restoring Fulton Street and Grand Avenue. This week, neighbors can expect to see:
- Backfilling excavations
- Restoration activities
Last week crews successfully completed tie-in activities on Fulton Street and Grand Avenue. This week, neighbors can expect to see:
- Welding activities
- Wrapping activities
- Backfilling excavations
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue
Last week crews continued installing infrastructure in the intersection of Fulton Street and Grand Avenue. and This week, neighbors can expect to see:
- Continued installation of infrastructure.
- Welding activities.
- Backfilling excavations.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
INTERMITTENT ROAD CLOSURES STARTING SATURDAY OCTOBER 05TH THROUGH SUNDAY OCTOBER 06TH FOR FULTON STREET, GRAND AVENUE, PUTNAM AVENUE AND, LEFFERTS PLACE.
Last week crews continued installing infrastructure in the intersection of Fulton Street and Grand Avenue. and This week, neighbors can expect to see:
- Continued installation of infrastructure.
- Welding activities.
- Backfilling excavations.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
Last week crews completed quality assurance testing and continued installing infrastructure in the intersection of Fulton Street and Grand Avenue. and This week, neighbors can expect to see:
- Beginning on September 11th through September 13th, crews will be performing quality assurance testing of the infrastructure which will require 24/7 presence of crews on-site.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued installing infrastructure in the intersection of Fulton Street and Grand Avenue. and This week, neighbors can expect to see:
- Beginning on September 11th through September 13th, crews will be performing quality assurance testing of the infrastructure which will require 24/7 presence of crews on-site.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating in the intersection of Fulton Street and Grand Avenue. and This week, neighbors can expect to see:
- No work on: Monday, September 2nd, 2024.
- Begin installing upgraded infrastructure within the roadway and/or sidewalks in the intersection of Fulton Street and Grand Avenue.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating in the intersection of Fulton Street and Grand Avenue. and This week, neighbors can expect to see:
- Begin installing upgraded infrastructure within the roadway and/or sidewalks in the intersection of Fulton Street and Grand Avenue.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating in the intersection of Fulton Street and Grand Avenue. and This week, neighbors can expect to see:
- Continued excavations and removal of infrastructure within the roadway and/or sidewalks in the intersection of Fulton Street and Grand Avenue.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating in the intersection of Fulton Street and Grand Avenue. and This week, neighbors can expect to see:
- Continued excavations and removal of infrastructure within the roadway and/or sidewalks in the intersection of Fulton Street and Grand Avenue.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating in the intersection of Fulton Street and Grand Avenue. and This week, neighbors can expect to see:
- Continued excavations and removal of infrastructure within the roadway and/or sidewalks in the intersection of Fulton Street and Grand Avenue.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews began excavating into the intersection of Fulton Street and Grand Avenue. and This week, neighbors can expect to see:
- Continued excavations and installation of infrastructure within the roadway and/or sidewalks in vicinity of Fulton Street and Grand Avenue.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued installing and testing upgraded infrastructure vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavations and installation of infrastructure within the roadway and/or sidewalks in vicinity of Fulton Street and Grand Avenue.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued installing and testing upgraded infrastructure vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavations and installation of infrastructure within the roadway and/or sidewalks in vicinity of Fulton Street and Grand Avenue.
- Backfilling activities.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued installing and testing upgraded infrastructure vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavations and installation of infrastructure within the roadway and/or sidewalks in vicinity of Fulton Street and Grand Avenue.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews completed quality assurance testing and continued installing upgraded infrastructure vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavations and backfilling within the roadway and/or sidewalks in vicinity of Fulton Street and Grand Avenue.
- No work on July4th, 2024.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating and installed upgraded infrastructure in the vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavations and installation of upgraded infrastructure in the roadway and/or sidewalk area at the intersection of Fulton and Grand heading North towards Putnam.
- 24- Hour crew presence for quality assurance testing Wednesday evening into Thursday evening.
- Temporary road closures and traffic impacts near the work zone on Fulton Street and Grand Avenue.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating and installed upgraded infrastructure in the vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavations and installation of upgraded infrastructure in the roadway and/or sidewalk area at the intersection of Fulton and Grand heading North towards Putnam.
- Temporary road closures and traffic impacts near the work zone.
- Work at the remote opening locations.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating and welding in the vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavations and welding activities in the roadway and/or sidewalk area at the intersection of Fulton and Grand heading North towards Putnam.
- Temporary road closures and traffic impacts near the work zone.
- Work at the remote opening locations.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating and welding in the vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavations and welding activities in the roadway and/or sidewalk area at the intersection of Fulton and Grand heading North towards Putnam.
- Temporary road closures and traffic impacts near the work zone.
- Work at the remote opening locations.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating and welding in the vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavations and welding activities in the roadway and/or sidewalk area near Fulton Street & Grand Avenue.
- Temporary road closures and traffic impacts near the work zone.
-
No work on Monday, May 27, 2024.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating and welding in the vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavations and welding activities in the roadway and/or sidewalk area near Fulton Street & Grand Avenue.
- Temporary road closures and traffic impacts near the work zone.
- RO5 on Bedford Avenue between Myrtle Avenue and Park Avenue beginning on 05/20/2024.
*IMPORTANT PARKING INFORMATION: There will be parking impacts near work zones and cars parked in work zones will be towed at the owner's expense. Please use alternative parking areas/streets if necessary.
Last week crews continued excavating the trench in the vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavation in the roadway and/or sidewalk area near Fulton Street & Grand Avenue.
- Temporary road closures and traffic impacts near the work zone.
Last week crews continued excavating the trench in the vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavation in the roadway and/or sidewalk area near Fulton Street & Grand Avenue.
- Support from National Grid's Corrosion Team.
- Temporary road closures and traffic impacts near the work zone.
Last week crews continued excavating the trench in the vicinity of Fulton Street & Grand Avenue. This week, neighbors can expect to see:
- Continued excavation in the roadway and/or sidewalk area near Fulton Street & Grand Avenue.
- Temporary road closures and traffic impacts near the work zone.
This week construction will begin in vicinity of Fulton Street & Grand Avenue. The community can expect to see:
- Mobilization of materials near the work zone.
- Crews excavating the roadway and/or sidewalks.
- Temporary road closures and traffic impacts near the work zone.