We are pleased to note that we have completed work on the Corona Maintenance - 2nd Ward Project. This work increased flexibility and reliability in the local infrastructure system in Corona. We sincerely appreciate your patience and understanding while we completed this important work in your community. For any questions or comments about this work, please email box.qnprojects@nationalgrid.com.

Last week our construction team continued restoration of sidewalks and curbs in areas affected by project construction. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Final restoration of the road in affected areas

Last week our construction team continued road restoration in affected areas. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Concrete restoration on sidewalks and final mill and pave, weather permitting

Last week our construction team continued road restoration on 98th St, 97th Place, Alstyne Avenue and Corona Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Concrete restoration on sidewalks and final mill and pave

Last week our construction team continued infrastructure testing on Alstyne Avenue and Corona Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Component installation on installed infrastructure
  • Survey of installed infrastructure
  • Continued backfilling and paving

Last week our construction team continued infrastructure installation and testing on Alstyne Avenue and Corona Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Component installation on installed infrastructure
  • Testing and survey of installed infrastructure
  • Continued backfilling and paving

 

Last week our construction team continued infrastructure installation in the Corona Avenue - 98th Street intersection and on 98th Street between Alstyne Avenue and Corona Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Backfilling in the Corona Avenue - 98th Street intersection
  • Testing and survey of installed infrastructure
  • Infrastructure installation on 98th Street near the Alstyne Avenue intersection
  • Infrastructure installation in the 98th Street - Alstyne Avenue intersection

Last week our construction team continued infrastructure installation in the Corona Avenue - 98th Street intersection and on 98th Street between Alstyne Avenue and Corona Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation in the Corona Avenue - 98th Street intersection
  • Infrastructure installation in the 98th Street - Alstyne intersection

Happy New Year! Hope you enjoyed your holidays last week.

Work resumes this week. You can expect to see:  

  • Continued infrastructure installation in the Corona Avenue - 98th Street intersection
     

2022

No work scheduled this week. Happy New Year!

Last week our construction team continued infrastructure installation in the Corona Avenue - 98th Street intersection and completed road and sidewalk restoration on 98th Street in areas where infrastructure installation has been completed. Please note that there will be a break in construction from December 19 until January 3. During this time our project phone line and email address will continue to be periodically monitored so please feel free to reach out.
 

When work resumes on January 3 neighbors can expect to see:

  • Continued infrastructure installation in the Corona Avenue - 98th Street intersection

 

Last week our construction team continued main installation on 98th Street between Corona Avenue and Alstyne Avenue and completed commissioning activities on 98th Street between Corona Avenue and 45th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation and backfill on 98th Street between Alstyne Avenue and Corona Avenue
  • Excavation in the Corona Avenue - 98th Street intersection

Last week our construction team continued work on 98th Street between Corona Avenue and Alstyne Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Commissioning activities and temporary road restoration in the 98th Street - 45th Avenue intersection.
  • Excavation and infrastructure installation on 98th Street between Alstyne Avenue and Corona Avenue

Last week our construction team continued work on 98th Street between 45th Avenue and Alstyne Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Excavation and infrastructure installation on 98th Street between Alstyne Avenue and Corona Avenue
  • Excavation and infrastructure installation in the Corona Avenue - 98th Street intersection
  • Backfilling and temporary road restoration on 98th Street between 45th Avenue and Corona Avenue.

Last week our construction team continued work on 98th Street between 45th Avenue and Corona Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Excavation and infrastructure installation on 98th Street between Alstyne Avenue and Corona Avenue
  • Service offsets on 98th St between Alstyne and 45th Ave (if your service is offset you will be re-lit the same day.  Individual notifications will be made)
  • Infrastructure installation on 98th Street between 45th Avenue and Corona Avenue.

Last week our construction team began work on 98th Street between 45th Avenue and Corona Avenue Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Excavation and infrastructure in the 98th Street - Alstyne Avenue intersection
  • Possible excavation and infrastructure installation on 98th Street between Alstyne Avenue and Corona Avenue
  • Excavation and infrastructure installation on 98th Street between 45th Avenue and Corona Avenue.

Last week our construction team completed work on 98th Street south of 50th Avenue and continued excavation and infrastructure installation on 98th Street north of 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Excavation and infrastructure in the 98th Street - Alstyne Avenue intersection
  • Possible excavation and infrastructure installation on 98th Street between Alstyne Avenue and Corona Avenue
  • Excavation and infrastructure installation on 45th Avenue between 98th Street and 97th Place

 

Last week our construction team continued backfilling on 98th Street south of 50th Avenue and continued excavation and infrastructure installation on 98th Street north of 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Backfill and temporary restoration on 98th Street between 50th Avenue and Christie Avenue
  • Infrastructure installation on 98th Street between 50th Avenue and Corona Avenue
  • Excavation and possible infrastructure in the 98th Street - Alstyne Avenue intersection

 

Last week our construction team began backfilling on 98th Street south of 50th Avenue and continued excavation and infrastructure installation on 98th Street north of 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Continued commissioning activities on 98th Street between 50th Avenue and Christie Avenue and on Christie Avenue between 97th Place and 98th Street
  • Infrastructure installation on 98th Street between 50th Avenue and Corona Avenue
  • Infrastructure installation in the 98th Street - Alstyne Avenue intersection

Last week our construction team continued commission activities south of 50th Avenue and began infrastructure installation on 98th Street north of 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Continued commissioning activities on 98th Street between 50th Avenue and Christie Avenue and on Christie Avenue between 97th Place and 98th Street
  • Infrastructure installation on 98th Street between 50th Avenue and Corona Avenue

Last week our construction team completed infrastructure testing on 98th Street between 50th Avenue and Christie Avenue and continued work in the 97th Place - Christie Avenue intersection. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Continued commissioning activities on 98th Street between 50th Avenue and Christie Avenue and on Christie Avenue between 97th Place and 98th Street
  • Infrastructure installation on 98th Street between 50th Avenue and Alstyne Avenue

*Construction schedule is subject to change

Last week our construction team conducted infrastructure testing on 98th Street between 50th Avenue and Christie Avenue and continued work in the 97th Place - Christie Avenue intersection. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Continued infrastructure testing and the start of commissioning activities on 98th Street between 50th Avenue and Christie Avenue and on Christie Avenue between 97th Place and 98th Street

Last week our construction team prepared for infrastructure testing on 98th Street between 50th Avenue and Christie Avenue and continued work in the 97th Place - Christie Avenue intersection. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure testing on 98th Street between 50th Avenue and Christie Avenue
  • Continued work on Christie Avenue between 97th Place and 98th Street

Last week our construction team continued infrastructure installation on 98th Street between 50th Avenue and Christie Avenue and continued work in the 97th Place - Christie Avenue intersection. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation and possible testing on 98th Street between 50th Avenue and Christie Avenue
  • Infrastructure installation on 98th Street between 50th Avenue and Alstyne Avenue
  • Continued work on Christie Avenue between 97th Place and 98th Street

Last week our construction team continued infrastructure installation on 98th Street between 50th Avenue and Christie Avenue and continued work on the 97th Place - Christie Avenue intersection. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Excavation and infrastructure installation on Christie Avenue between 97th Place and 98th Street
  • Excavation on 98th Street between 50th Avenue and Alstyne Avenue

Last week our construction team continued infrastructure installation on 98th Street between 50th Avenue and Christie Avenue and continued work in the 97th Place - Christie Avenue intersection. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue.
  • Infrastructure installation at the 97th Place - Christie Avenue intersection
  • Excavation and possible infrastructure installation on 98th Street between 50th Avenue and Alstyne Avenue

Last week our construction team continued infrastructure installation on 98th Street between 50th Avenue and Christie Avenue, excavated on 98th Street north of 50th Avenue, and continued work in the 97th Place - Christie Avenue intersection. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue.
  • Construction activity at the 97th Place - Christie Avenue intersection
  • Excavating on 98th Street between 50th Avenue and Alstyne Avenue

Last week our construction team continued infrastructure installation on 98th Street between 50th Avenue and Christie Avenue and continued work on the 97th Place - Christie Avenue intersection. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue.
  • Construction activity at the 97th Place - Christie Avenue intersection
  • Excavating on 98th Street between 50th Avenue and Alstyne Avenue

Last week our construction team continued infrastructure installation on 98th Street between 50th Avenue and Christie Avenue and continued work in the 97th Place - Christie Avenue intersection. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Construction activity at the 97th Place - Christie Avenue intersection
  • Excavation and infrastructure installation on 98th Street between 50th Avenue and Alstyne Avenue

Last week our construction team continued backfilling on 50th Avenue, infrastructure installation on 98th Street between 50th Avenue and Christie Avenue, and continued excavating on 98th Street north of 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue.
  • Construction activity at the 97th Place - Christie Avenue intersection

Last week our construction team continued backfilling on 50th Avenue, infrastructure installation on 98th Street between 50th Avenue and Christie Avenue, and continued excavating on 98th Street north of 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Backfilling and temporary restoration on 50th Avenue between 97th Place and 98th Street. Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue.

Last week our construction team continued infrastructure installation on 98th Street between 50th Avenue and Christie Avenue and began sawcutting on 98th Street north of 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Backfilling and temporary restoration on 50th Avenue between 97th Place and 98th Street
  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Trenching and possible infrastructure installation on 98th Street between 50th Avenue and Alstyne Avenue

Last week our construction team continued infrastructure installation on 97th Place, 50th Avenue, and 98th Street. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Infrastructure installation on Christie Avenue and 97th Place
  • Trenching and possible infrastructure installation on 98th Street between 50th Avenue and Alstyne Avenue

Last week our construction team continued infrastructure installation on 97th Place and 50th Avenue and trenching on 98th Street. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

Please note, our crews will not be working on July 4th.

This week neighbors can expect to see:

  • Backfilling on 50th Avenue between 97th Place and 98th Street
  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Infrastructure installation on Christie Avenue and 97th Place
  • Trenching on 98th Street between 50th Avenue and Alstyne Avenue

Last week our construction team continued infrastructure installation on 97th Place and 50th Avenue and trenching on 98th Street. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Backfilling on 50th Avenue between 97th Place and 98th Street
  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Infrastructure installation on Christie Avenue and 97th Place
  • Test pitting on 98th Street north of 50th Avenue.

Last week our construction team continued infrastructure installation on 97th Place and 50th Avenue and trenching on 98th Street. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Backfilling and infrastructure installation on 50th Avenue between 97th Place and 98th Street.
  • Infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Infrastructure installation on Christie Avenue and 97th Place.
  • Test pitting on 98th Street north of 50th Avenue.

Last week our construction team continued infrastructure installation on 97th Place and 50th Avenue and began trenching on 98th Street. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Backfilling on 97th Place between Christie Avenue and 50th Avenue
  • Infrastructure installation on 50th Avenue between 97th Place and 98th Street
  • Trenching and infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Test pitting on 98th Street north of 50th Avenue

Last week our construction team continued infrastructure installation on 97th Place and 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation and backfilling on 97th Place between Christie Avenue and 50th Avenue
  • Infrastructure installation on 50th Avenue between 97th Place and 98th Street
  • Trenching and possible infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Test pitting on 98th Street north of 50th Avenue

Last week our construction team continued infrastructure installation on 97th Place and 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation and backfill on 97th Place between Christie Avenue and 50th Avenue
  • Trenching and infrastructure installation on 50th Avenue between 97th Place and 98th Street
  • Trenching and possible infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Test pitting on 98th Street north of 50th Avenue

Last week our construction team continued infrastructure installation on 97th Place and 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation and backfill on 97th Place between Christie Avenue and 50th Avenue
  • Trenching and infrastructure installation on 50th Avenue between 97th Place and 98th Street
  • Trenching and possible infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Test pitting on 98th Street north of 50th Avenue

Last week our construction team continued infrastructure installation on 97th Place between Christie Avenue and 50th Avenue, and trenching on 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Backfilling and temporary restoration on 97th Place between Christie Avenue and 50th Avenue
  • Trenching and infrastructure installation on 50th Avenue between 97th Place and 98th Street
  • Trenching and possible infrastructure installation on 98th Street between 50th Avenue and Christie Avenue
  • Test pitting on 98th Street north of 50th Avenue

Last week our construction team continued infrastructure installation on 97th Place between Christie Avenue and 50th Avenue, and trenching on 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Trenching and infrastructure installation on 50th Avenue between 97th Place and 98th Street
  • Trenching on 98th Street between 50th Avenue and Christie Avenue
  • Test pitting on 98th Street between 50th Avenue and Alstyne Avenue

Last week our construction team continued infrastructure installation on 97th Place between Christie Avenue and 50th Avenue, and began trenching on 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Continued infrastructure installation on 97th Place between Christie Avenue and 50th Avenue
  • Trenching and  infrastructure installation on 50th Avenue between 97th Place and 98th Street
  • Possible trenching on 98th Street between 50th Avenue and Christie Avenue

Last week our construction team began infrastructure installation on 97th Place between Christie Avenue and 50th Avenue, and test pitting on both Christie Avenue and 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Continued infrastructure installation on 97th Place between Christie Avenue and 50th Avenue
  • Trenching on 50th Avenue between 97th Place and 98th Street
  • Possible infrastructure installation on 50th Avenue

Last week our construction team continued trenching on 97th Place between Christie Avenue and 50th Avenue, and test pitting on both Christie Avenue and 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Infrastructure installation on 97th Place between Christie Avenue and 50th Avenue
  • Continued test pitting on 50th Avenue and Christie Avenue
  • Possible test pitting on 98th Street north of 50th Avenue

Last week our construction team continued trenching on 97th Place between Christie Avenue and 50th Avenue, and test pitting on both Christie Avenue and 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Continued trenching and infrastructure installation on 97th Place between Christie Avenue and 50th Avenue
  • Continued test pitting on 50th Avenue and Christie Avenue
  • Possible test pitting on 98th Street north of 50th Avenue

Last week our construction team continued trenching on 97th Place between Christie Avenue and 50th Avenue, and test pitting on both Christie Avenue and 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Continued trenching on 97th Place between Christie Avenue and 50th Avenue
  • Continued test pitting on 50th Avenue and Christie Avenue
  • Possible test pitting on 98th Street north of 50th Avenue

Last week our construction team began trenching on 97th Place between Christie Avenue and 50th Avenue, and test pitting on both Christie Avenue and 50th Avenue. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Continued trenching on 97th Place between Christie Avenue and 50th Avenue
  • Continued test pitting on Christie Avenue and on 50th Avenue

This week our construction team is starting work on the Corona - Second Ward Maintenance Project. Please note that traffic patterns and parking availability will be affected near active work areas. There will be flaggers present to redirect traffic as necessary.

This week neighbors can expect to see:

  • Trenching on 97th Place between Christie Avenue and 50th Avenue
  • Test pitting on Christie Avenue between 98th Street and 97th Street and on 50th Avenue between 97th Street and 98th Street