Eversource and National Grid Complete Ready Path Solution to Strengthen Greater Boston’s Electric Reliability and Support Retirement of Mystic Generating Station in 2024

Jun 15, 2023 - 1:00 PM

Categories:

Massachusetts

Clean Energy

Community

News-Image

TEWKSBURY, MA – As part of an innovative collaboration to improve the reliability of the region’s electric system in advance of the expected retirement of the fossil-fuel fired Mystic Generating Station early next year, Eversource and National Grid today announced the completion ahead of schedule of the Ready Path Solution.

National Grid and Eversource partnered on the project to ensure reliable service for customers across the region.

“Our partnership to complete this project ahead of schedule is an important step forward for upgrading regional transmission infrastructure, which is the backbone of the electric grid and critical to achieving decarbonization and electrification goals in Massachusetts,” said Bill Quinlan, Eversource President of Transmission and Offshore Wind Projects. “Supporting the retirement of the fossil fuel-fired Mystic Generating Station, the Ready Path Solution will save customers millions of dollars each year and facilitate a cleaner and more resilient grid.”

“National Grid and Eversource partnered to build a project that was innovative, cost-effective and completed ahead of-time,” said Stephen Woerner, President of National Grid New England. “We have built a project that will meet the region’s reliability needs and allow the timely closure of the Mystic station.  New England’s electric grid must continue to evolve in order to maintain system reliability while ensuring customers have access to new sources of clean, renewable energy. This project helps take that evolution a step further.”

The Ready Path Solution was competitively chosen from several alternatives by ISO New England (ISO-NE), the region’s independent power grid manager. With an installed cost of $49 million, it was selected as the most cost-effective solution to maintain grid reliability following the retirement of the Mystic Generating Station, a 2,000-megawatt fossil fuel-fired power plant in Everett. The Mystic facility is scheduled to retire in 2024 and would cost New England customers an estimated $175 million annually to keep the station available for system reliability purposes.

According to ISO-NE, without upgrades to the region’s electric grid, the closure of the Mystic Generating Station would create significant reliability risks for customers in the Boston area, including overloaded transmission lines and system instability.

The project was built entirely within existing National Grid and Eversource substations in Cambridge, Haverhill, Amesbury, and Tewksbury. In 2022, National Grid completed control system upgrades at the Amesbury and Haverhill substations that will allow the electric transmission network to respond reliably and avert transmission line overloads. Eversource also completed installation of equipment at its existing North Cambridge substation to direct power flows more efficiently.

National Grid has now completed work on the final piece of the Ready Path Solution, installing equipment at its substation in Tewksbury. The installation of a Static Synchronous Compensator, also known as a STATCOM, will provide the transmission network with voltage support and reactive power control. With the completion of this work, the full project was put into service on June 7, 2023.

For more information on the Ready Path Solution, visit www.greaterbostonreadypath.com.

About National Grid

National Grid (NYSE: NGG) is an electricity, natural gas, and clean energy delivery company serving more than 20 million people through our networks in New York and Massachusetts. National Grid is focused on building a smarter, stronger, cleaner energy future — transforming our networks with more reliable and resilient energy solutions to meet state climate goals and reduce greenhouse gas emissions.

For more information, please visit our website, follow us on X (formerly Twitter), watch us on YouTube, like us on Facebook and find us on Instagram.